October 15, 2026
"The Linville Road detour is scheduled for the final phase of the project timeline, assuming there are no changes." NCDOT resident engineer Jacob Harris wrote that to the Northwest Observer in June 2025, just as crews put up temporary signal poles at NC 68 and NC 150. The same article gave mid-September 2026 as the completion date for the nearly $10.5 million project. It's now October 2026, and that date has passed. The order of the work hasn't changed, so the part you'll feel most behind the wheel is still the part that comes last.
On paper, the project is STIP R-5725. It covers NC 68 from Fogleman Road to NC 150/Oak Ridge Road, and NCDOT describes its purpose as improving safety and traffic flow while addressing bicycle and pedestrian connections. NCDOT awarded the contract to Yates Construction on July 5, 2023, for $10,497,020.93.
The start date moved several times before any dirt did. In March 2024, the Town of Oak Ridge passed along NCDOT's estimate that roadwork would begin in late summer or early fall of 2024 and take 24 to 30 months. Utility relocations involving Piedmont Natural Gas, AT&T, Charter Spectrum and Duke Energy still had to be finished first. By July 2024, those relocations were running long, and the likely start had shifted to spring 2025. In January 2025, NCDOT said one utility was still left to move and pushed the earliest start to April 2025. The construction estimate was still 24 to 30 months.
The intersection became an NCDOT work zone on June 18, 2025, and lane closures for drain pipe installation began June 30, 2025. If you count 24 months from that start, you land in mid-2027, not September 2026. Even so, the September 2026 date kept appearing in print. The Northwest Observer repeated it in December 2025 while reporting that NCDOT was leasing a vacant lot beside the former Josie's Boutique on NC 150 as an equipment staging area.
The newest official schedule in the public record is a construction status table in a High Point MPO agenda dated February 17, 2026. As of that report, the contract was 28% complete, storm drain work was finished, and the completion date was listed as March 19, 2027. So about eight months after lane closures began, a little over a quarter of the contract was done. No newer status table turned up, so take the March 2027 date as the February estimate, not a promise.
If the intersection doesn't look very different yet, that's because most of the work so far has been underground or behind barrier walls.
In 2025, the Town's project updates read like a drainage project. Crews installed storm drain pipe at the south end of NC 68, laid temporary asphalt from Linville Road to Marketplace Drive so traffic could shift to the center lane, and graded north of Fogleman Road for curb and gutter. Barrier rails went up in three stretches. One runs from just north of DeVaney Dentistry to NC 150. Another starts across from CVS and wraps along NC 68 past Central Baptist Church on the Oak Ridge Military Academy side. The third runs from across the Allen Tate office to Carolina Priority Care. The gas station entrance closest to the intersection closed until further notice.
In 2026, the work started showing up on the road surface:
The missing left turn onto Linville is the first change built for the roundabout. The Town's April 22 update said drivers should continue to the signal at NC 68 and NC 150 to make the turn, and that traffic flow would stay affected until the roundabout is fully operational.
Here is where the project stands, based on the public record as of mid-September 2026.
| Piece of the project | Status in the public record |
|---|---|
| Utility relocation | Finished before construction started in 2025 |
| Storm drains | Listed as complete in the February 2026 MPO table |
| Barrier walls and temporary widening | Installed in 2025; some wall sections removed in April 2026 |
| Paving along NC 68 | Multiple rounds through September 14, 2026 |
| Roundabout at NC 68 and Linville Road | No start date as of the Town's July 31, 2026 update |
| Linville Road detour | Described by NCDOT in 2025 as the final phase |
| Roundabout at NC 150 and Marketplace Drive | No public timeline found |
| Removal of three of four NC 150-to-NC 68 slip lanes | Part of the plan; no date published |
The Town's July 31 update says the start date for the Linville Road roundabout had not been determined. It also says the Town and NCDOT would work with Yates Construction to limit traffic impact during afternoon school dismissal, and that morning drop-off shouldn't be affected because construction won't begin until 9 a.m. No later update confirms whether that work has started, so the Town's project page is the place to check before planning around it.
The second roundabout will sit on NC 150 at Marketplace Drive, near Sherwin-Williams and across from the Oak Ridge Commons entrance. The plan also eliminates three of the four slip lanes from NC 150 onto NC 68. Back in 2024, NCDOT listed the impacts it expected during construction. They included sidewalk closures with pedestrian detours, a single entryway into the shopping centers, and a traffic detour at Linville Road and NC 68. The first two are temporary inconveniences. The detour is the change Harris pointed to in 2025, and it's still ahead.
The project has a longer history than its cones. By June 2025, more than five years had passed since the Oak Ridge Town Council endorsed NCDOT's plans for the commercial district. The Northwest Observer described the two roundabouts, new signals and pedestrian crosswalks at Highways 68 and 150 as part of the town's effort to slow traffic and promote a village atmosphere centered on pedestrians and cyclists. Coverage from April 2025 described the same pieces. Earlier, in July 2024, the paper reported that the Town planned to share the cost of sidewalks and aesthetic improvements on top of NCDOT's signal and crosswalk work. That cost-sharing detail is two years old, so it may have changed.
The roundabout at Linville and the loss of the left turn lane come from the same goal. The slip-lane removal does too. Each one gives up a little of the old free-flowing movement in exchange for slower, more predictable traffic around Oak Ridge Commons, Marketplace Shopping Center and the stores near Bojangles and Starbucks.
The rules of the work zone have been steady since construction began, and they're the most useful thing to know for the months ahead.
The Town posts closures on its project page and keeps the NCDOT plan summary on its town news page. The next update worth watching for is a start date for the Linville Road roundabout.
I follow changes like this one closely because a new traffic pattern can affect daily routines and how a home's location feels day to day. If you'd like to talk through how the finished crossroads at 68 and 150 might fit into your own plans in Oak Ridge, Melody Davis is glad to help. Let's Connect.
Stay up to date on the latest real estate trends.
Oak Ridge NC real estate
Things to do in Greensboro NC
moving to Greensboro NC, Greensboro NC pros and cons, Greensboro property taxes, Greensboro home prices 2026
Whether you're buying your first home or making your next move, Melody provides trusted guidance, personalized service, and a passion for helping families achieve their homeownership goals.